Projects and Estimated Completion (Construction schedules are subject to change)

Capital Improvement Project Awards

 Water Pressure Increases

 City Facilities and Culture Leisure Projects

To preserve competitive equity of both potential design professionals and contractors, the Engineering Department does not make individual notification for advertisement of capital improvement facility projects nor does it maintain a “pre-approved” list for professional services. When advertised, projects will be posted on the City Purchasing Web site and Carrollton Leader. Projects may also be posted on online subscription sites that include DemandStar and iSqft. Interested parties are encouraged to refer to the link below for general schedules of all current and planned facility projects. Additionally, engineering staff is available to discuss any project in detail and answer related questions. However, it remains the sole responsibility of the prospective design professional, contractor, vendor or other related party to monitor the referenced resources for actual project advertisement.   

  • Hebron-Josey Library Remodel - Design Underway; Construction scheduled for July, 2014*
  • Sandy Lake Service Center Administration Building - Construction Scheduled for Late Fall 2014.
  • New Carrollton Police Station - Design Request for Qualifications Scheduled for July, 2014*
  • Senior Center Expansion - Design Request for Qualifications Scheduled for July, 2014*

           *All dates tentative and subject to change without notice.

     Street Projects

  • FM 544 - Josey to Dozier - Delayed by TxDOT until 2014
  • Old Mill Road, Briargrove to Marsh Reconstruction - Completion February 2015
  • Alley Reconstruction Projects 2012 - Completion September 2014 

Project #2: Willow Place (Carmel to Carmel), Southern Place (Carmel to Carmel), Springwood Place (Carmel to Carmel), Oxfordshire (Staffordshire to Old Denton), Old Denton (Oxfordshire #1 to Nottingham), Hampshire (Hampshire to Oxfordshire #1), Miramar (Oxfordshire #1 to Staffordshire), Earlshire #2 (Wiltshire to Miramar), Wiltshire (Berkshire to 1101 Wiltshire), Rosehill #3 (Peters Colony to Rosehill) and Rosehill #5 (Peters Colony to Rosehill). 

Project #3:  Toluca (Toluca to Guerrero), Taxco (Toluca to Guerrero), Pueblo (Tampico to Guerrero), Eldorado (Tampico to Guerrero), Cordoba (Scott Mill to Cordoba), Guerrero (Cordoba to north end), Southampton #1 (Standridge to Elizabeth), Hartford #2 (Standridge to Chesterfield), Rosemeade Circle (Rosemeade Circle to Rosemeade Circle), Rosemeade (Highgate to Woodside), Kentwood #1 (Highgate to Woodside), Camden Way #1 (Highgate to Woodside) and Chesham Drive (Highgate to Woodside).

Traffic Operations

  • Miscellaneous transportation projects Right turn lanes, improved underpasses (i.e. Sandy Lake Road and I-35E), synchronization of traffic signals Ongoing 
  • New Signals and Reconstruction - Ongoing 
  • Right-of-Way and Intersection Improvements - Ongoing 
  • Signal Retiming and Upgrades - Ongoing
  • Rosemeade Parkway Street Light Project (Josey Lane to Kelly Blvd) - Ongoing

Drainage and Water Utilities  

  • Santa Rosa Heights, and Barton Road Sewer Replacement - Completion October 2014
  • Indian Creek Interceptor Sewer Rehabilitation - Completion September 2014
  • Champion Drive and IH 35E Lift Station Upgrades - Completion October 2014 
  • Carrollton Downs, Phase 1 - Alleys and Sanitary Sewer Rehabilitation - Completion January 2015 

Neighborhood and Urban Design Projects    

  • Woodlake #3 Street and Sanitary Sewer Reconstruction - Braddons, Wellington, Lymington, Kings, Meadfoot, Rose Hill, Albert, and Victoria (all streets west of Furneaux Lane) - Start Summer 2014

 Regional Projects

  • PGBT Interchange Improvements - TBD

Completed Projects 2014

  • Hill 'N Dale, Phase 2 Pavement Rehabilitation - Completed September 2014
  • Water Replacements 2013 - Carter Drive, (North of PGBT), Eisenhower (South of Frankford), Halsey Way, Crescent Drive, Rosemeade (Cromwell to Standridge), - Completed May 2014
  • Rosemeade Water Line Replacements (Cromwell to Standridge & Josey to Furneaux) Completed April 2014   
  • Downtown Trail, Phase 1 (Crosby Road to Hutton Branch) - Completed April, 2014
  • Two Worlds of Keller Springs Village Street Reconstruction, Phase 2 - (Via Los Altos, Via Miramonte, Via Bravo, Via Sonoma, Via LaPaloma, Via Ventura, Via Blanca, Via Del Mar & Via Ballena) - Completed January 2014
  • Hill 'N Dale Reconstruction, Phase 1 (Sherwood Lane) - Completed January 2014

Completed Projects 2013

  • Alley Replacement 2012-1: Timberleaf #2, Timberleaf #3, Brighton, Mayflower, Walker, Ginger,  Arundel, Chamberlain #2, Rambling Ridge #3, Vista Glen, Rosemeade #2, Bishop Hill, and Woodcreek #1.
  • Plano Parkway (Parker Road North to City Limits - addition of inside lanes) - Completed September 2013
  • Hutton Branch Sewer Rehabilitation (Josey to Valley Mill) - Completed September 2013
  • Two Worlds of Keller Springs Street Reconstruction - Phase 3 - (Via Avenida, Via Del Plata, Via Avenida Circle, Via Estrada - Completed September 2013
  • Street Replacements 2012 - Rolling Hills, Rayswood, Scott Mill (North of Frankford) - Completed July 2013
  • Hartford Drive - Completed July 2013
  • Crosby Sewer (Hutton to IH35E) - Completed March 2013
  • Furneaux Creek Channel Improvements - Old Denton to Mccoy - Completed March 2013
  • Furneaux Creek Channel Improvements - Rosemeade to Hebron - Completed March 2013
  • Completed Projects 2012

    • Furneaux Creek Channel Improvements - Frankford to Kelly - Completed June 2012     
    • Cherokee Path Sewer - Completed June 2012
    • High Country Drainage Improvements at Meadow Lane - Completed June 2012
    • Water Replacements 2011 - Villas of Josey Ranch Apts., Parkside Village Apts., Province Drive, Gallante Drive, Cologne Drive, and Sonata Drive - Completed May 2012
    • Canterbury Drive Reconstruction - Completed April 2012
    • Monetary Lane Lift Station - Completed October 2012
    • Two Worlds of Keller Springs Village Street Reconstruction, Phase I - (Willowgate Lane, Via Corona, Via Cordova, Via Dos Mundos, Via Balboa, Via Madonna, Via Valencia, and Via Catalina) - Completed November 2012
    • Diplomat Drive - Hutton to City Limits - Completed December 2012

     Completed Projects 2011    

    • Park Place Subdivision Phase II- Completed December 2011    
    • Downtown Retention Pond - Completed December 2011
    • Trinity Mills Road Reconstruction - Willowgate Lane to Midway Road - Completed January 2011
    • Furneaux Lane - Frankford to Winterberry - Completed January 2011
    • Water Replacements 2010 - Trinity Crossing Apts., Lakeshore Condominiums, County Trail Apts., Toulon Lane, Clermont Court, Lyon Court, and Gardanne - Completed June 2011
    • Alley Replacements - Rosemeade, Marble Falls, Somerville, Grapevine, Tierra Calle, Oakwood, Northridge, Northland, and Estates Way - Completed June 2011
    • Frankford - Standridge to Josey - Completed September 2011
    • Champion Circle - East of Hutton - Completed September 2011
    • IH35E Sewer (College to Sandy Lake) Completion July 2011
    • Crosby Road Reconstruction - Broadway to Josey - Completed October 2011
    • Fyke Road Lift Station - Completed October 2011
    • Dozier Road 12" Water Line - Completed November 2011

    Completed Projects 2010

    • Miscellaneous Water Improvements 2009 (Waterford & Tallows Apts.) - Completed May 2010 
    • Furneaux Creek Sanitary Sewer - Furneaux Lane to Branch Hollow - Completed May 2010
    • Dickerson Road - From Trininty Mills to Frankford - Completed June 2010
    • Furneaux Creek Channel Improvements & Sanitary Sewer - Frankford to Furneaux Lane - Completed June 2010    
    • Woodlake #3 (Highbury, Carlton, Abbey, Abbey Cove)- Completion June 2010
    • Midway Road - PGBT to Hebron - Inside Lanes - Completed 2010
    • Champion Drive - Completed September 2010
    • South Main Street - Belt Line to DART tracks - Completed October 2010
    • Park Place Subdivision, Phase I - Completed November 2010
    • Columbian Club Pump Station - Electrical & Pump Improvements - Completion December 2010

     Completed Projects 2009 

    • Columbian Club Pump Station Building and Piping Improvements - Completed February 2009
    • Tarpley Drive - From Simpson to south of Kellway - Completed April  2009
    • Peters Colony Road - From Paxton to Furneaux - Completed May 2009
    • North Transmission Line - Elm Fork Treatment Plant to Bobby Ballard Pump Station - Completed May 2009
    • Old Denton Road Reconstruction - Completed June 2009
    • Standridge Drive - From Rosemeade to Chesterfield - Completed August 2009 
    • Frances Perry Estates - Completed August 2009
    • Hutton Branch Channel Improvements - Josey to Kelly - Completed November 2009 
    • Miscellaneous Sewer Line Replacement (14 Locations) - Completed November 2009

    Completed Projects 2008

    • Kelly Boulevard (Interlocal Agreement with city of Dallas) - Rosemeade to Michaelangelo - Completed March 2008 
    • McCoy Road Reconstruction - Jackson to Trinity Mills - Completed January 2008 
    • Old Mill Road Completed February 2008 
    • McCoy Water Line Replacement - Keller Springs to Jackson - Completed January 2008 
    • Carrollton Highlands Street Reconstruction - Highland, Tartan, Balmoral, Perry (Belt Line to Crosby) - Completed February 2008 
    • Woodlake Pond Dredging - Completed June 2008
    • Belt Line Road Widening/Reconstruction - Maryland to Jackson - Completed July 2008 
    • Alley Reconstruction - Christie, Stefani Court, Jennifer Court, Winterberry, Furneaux, Lookout Place, Stainglass, Shannon, Shannon Court, and Courtland - Completed September 2008 
    • Belt Line Screening Wall - Sparling Way to Hersey - Completed October 2008 
    • Hutton Branch Sanitary Sewer Replacement - Vida del Plata to Country Square - Completed December 2008. 
    • Country Place Sewer Line Replacement - Completed December 2008

    Completed Projects 2007

    • Belt Line Road Reconstruction - Milam to Webb Chapel - Completed Feb. 2007 
    • Furneaux Creek Channel Improvements & Sanitary Sewer - Frankford to Woodlake Dam - Completed December 2007 
    • Kelly Boulevard Road Reconstruction - Keller Springs to Trinity Mills - Completed June 2007 
    • Marsh North Elevated Storage Tank - Completed Jan. 2007 
    • Miscellaneous Water & Sewer Lines 2005 - Various locations - Completed Feb. 2007 
    • Oak Creek Park Improvements - Completion Fall 2007 
    • Miscellaneous Water Line Replacement 2006 - Woodlake No. 2 & 4,Ridgecrest No. 1 - Completion Aug. 2007 
    • Parks Maintenance Facility - 2205 Sandy Lake Road (Rural America site) - Completed April 2007 
    • Rosemeade Pool Renovation -Completed June 2007 
    • Scott Mill Road Reconstruction - From Trinity Mills to Frankford - Completed March 2007 
    • Thomas Pool Renovation -Completed June 2007

    Completed Projects 2006

    • Alley Reconstruction - Timberleaf, Lands End, Plumdale, Ramblewood, Yorkshire, Dentonshire, Derbyshire Place, Austin & Lakewood - Completed July 2006 
    • Golden Bear Booster Pump Station - Tarpley Road - Completed March 2006 
    • Highland Creek Channel Improvement - Completed January 2006 
    • Holiday Park Street and Waterline Improvements Phase 2 - Foxcrost, Wintergreen, Burning Tree, School - Completed August 2006 
    • Sutter's Mill Street Reconstruction - From McCoy Road to cul-de-sac - Completed March 2006 
    • Kelly Boulevard Road Reconstruction - Belt Line Road to Columbian Club - Completed November 2006 
    • Crosby Estates Sanitary Sewer Phase 2 - Completed December 2006 
    • Hutton Branch Drainage - Keller Springs to Jamestown - Completed Dec. 2006

     Completed Projects 2005 

    • Alley Reconstruction - Osceola, Terry Way, Cherrywood, Geronimo Arrow, Conrad, Devon, Westminster, Hartford and Sancerre - Completed December 2005 
    • Broadway Street to Denton Drive Sanitary Sewer Replacement - Completed May 2005 
    • Crosby Estates Sanitary Sewer Phase 1 - Completed December 2005 
    • Dudley Branch Sanitary Sewer Segment 2 - Old Denton Road to Virginia Pine along Dudley Branch Creek - Completed August 2005 
    • Holiday Park Street and Waterline Improvements Phase 1 - Perry, Moonbeam, Appletree, Fairfax, Chevy Chase - Completed August 2005 
    • Rollingwood Estates Ph. 2 Paving and Sidewalk Improvements Completed April 2005 
    • Sandy Lake Road - PGBT to McInnish Park - Completed October 2005 
    • Statler/Haymeadow/Wildrose/Windhaven Street Reconstruction - Completed August 2005
  • Free viewers are required for some of the attached documents.
    They can be downloaded by clicking on the icons below.

    Download Acrobat Reader Download Flash Player Download QuickTime Download Windows Media Player Download Microsoft Silverlight Download Word Viewer Download Excel Viewer Download PowerPoint Viewer
    Last updated: 9/2/2014 4:29:42 PM